Project Overview
The National Naval Medical Center in Bethesda, Maryland, required immediate temporary medical swing space to facilitate a seamless transition for staff from existing buildings without disrupting ongoing medical services. This was the first step in a series of relocations and renovations planned over the next three years.

Client Needs
The project faced challenges such as limited parking, overlapping tradesmen tasks, and complex campus navigation. The Williams Scotsman team was tasked with managing these challenges while adhering to a critical schedule.

Why Modular Construction?
Williams Scotsman utilized modular construction techniques, specifically their Concurrent Construction™ methods, to expedite the project timeline by up to 50%.

Project Milestones and Solutions
Williams Scotsman provided two two-story modular buildings totaling 35,280 square feet. The buildings included specialized rooms for physical therapy, occupational therapy, chiropractic care, and general treatment. A Helical Pier Foundation System was used for stabilization, and interior features included automatic sliding glass doors and a lead-lined X-ray room.

Project Outcome
The project was completed on time with minimal disruption to campus traffic and operations. The successful installation marked the beginning of a series of upgrades to enhance the facility for military personnel.

Key Dates
Order Received: 9/8/08
Delivery: 10/3/08
Installation: 11/19/08

Client Testimonial
Raymond P. Molano, Senior Project Manager at Clark/Balfour Beatty, praised the project for its timely completion and safe execution, highlighting its importance in the broader renovation plan.
See more

Catalog excerpts

NATIONAL NAVAL MEDICAL CENTER - Bethesda, Maryland-1

PROJECT CASE HISTORY NATIONAL NAVAL MEDICAL CENTER Bethesda, Maryland Client Project The client’s need was immediate. The medical center had to move into new temporary space before Thanksgiving 2008 to allow ample time for the staff to transition from existing Why Modular? Permanent modular buildings can put your project on the fast track. With Williams Scotsman’s buildings to the medical swing space without interruption to Concurrent Construction™ on-going medical services. techniques, critical steps occur Client Need Temporary outpatient medical swing space was step one in a simultaneously resulting in up to 50% faster construction schedule. series of relocations and renovations the National Naval Medical Center will undergo over the next three years. Extremely limited parking, overlapping of multiple tradesmen completing their tasks at the center, and winding campus roads compounded the complexity of the project. The Williams Scotsman team smoothly navigated both the critical schedule and the challenge of a busy, crowded campus.

 Open the catalog to page 1
NATIONAL NAVAL MEDICAL CENTER - Bethesda, Maryland-2

NATIONAL NAUAL MEDICAL CENTER Bethesda, Maryland Williams Scotsman's Concurrent Construction™ Process Timeline CONCURRENT CONSTRUCTION™ - Nearly Half the Time! The Williams Scotsman solution Williams Scotsman supplied 2-two story modular buildings encompassing 35,280 square feet and for the medical swing space. A Helical Pier Foundation System was utilized to provide maximum stabilization. The buildings housed a physical therapy room, an occupational therapy room, a chiropractic room, and other general treatment rooms. Interior automatic sliding glass doors increased the staff and patients' ease...

 Open the catalog to page 2

All Williams Scotsman catalogs and technical brochures

Archived catalogs

  1. FBI Academy

    2  Pages

*Prices are pre-tax. They exclude delivery charges and customs duties and do not include additional charges for installation or activation options. Prices are indicative only and may vary by country, with changes to the cost of raw materials and exchange rates.