Project Overview: Ira Davenport Memorial Hospital in Bath, New York, aimed to relocate its rehabilitation department to a newly constructed building adjacent to the main hospital. This move was intended to differentiate its services from neighboring hospitals and allow for inpatient expansion.
Client Needs: The hospital required the new facility to be completed promptly to avoid patient referrals to external clinics and minimize revenue and operational disruptions. The construction needed to comply with state and New York Department of Health codes and aesthetically match the rural setting. Cost efficiency and a quick timeline were crucial, leading to the choice of Williams Scotsman’s modular Concurrent Construction™ process.
Construction Timeline: The modular project was completed in 5 months, compared to an estimated 8-10 months for traditional construction.
Milestones and Solution: The project involved constructing a free-standing rehabilitation department using eight 12’ x 50’ modules. The building featured a 4” brick facade and a 4’ high mansard roof to blend with existing facilities and serve as a focal point. An exterior glass vestibule was included as a windbreak.
Results: The rehabilitation center met all state and health code requirements and was completed in five months. It included a general office, patient waiting area, private treatment areas, and a core rehabilitation area with exercise equipment, hydrotherapy tubs, and a walking track. The modular construction process minimized disruption, allowing the hospital to maintain operations and revenue generation sooner than conventional methods.
See more

Catalog excerpts

IRA DAVENPORT MEMORIAL HOSPITAL-1

PROJECT CASE HISTORY IRA DAVENPORT MEMORIAL HOSPITAL Bath, New York Client Project Ira Davenport Memorial Hospital wanted to relocate its rehabilitation department to a newly constructed building adjacent to the main hospital facility. By providing a new free standing rehabilitation building, Ira Davenport could differentiate its program from neighboring hospitals and make room for much needed inpatient expansion within the hospital. Client Need The hospital needed construction of the new facility completed in a timely manner to avoid referring patients to alternate physical therapy clinics outside the area and more importantly, have a minimal impact on the overall revenue production and operations of the hospital. Also, the structure had to fully comply with both state and New York Department of Health buildings codes, and aesthetically blend in with existing facilities located in this rural area. Since the site was located in a rural remote area, and cost efficiency was vital, conventional construction timeline posed a grave concern in accommodating the hospital’s needs. Therefore, Williams Scotsman’s modular Concurrent Construction™ process became the ideal solution.

 Open the catalog to page 1
IRA DAVENPORT MEMORIAL HOSPITAL-2

Bath, New York The Williams Scotsman Solution A free-standing rehabilitation department was constructed using eight 12’ x 50’ modules. In order to blend in with existing facilities, and also serve as the MILESTONES IRA DAVENPORT MEMORIAL HOSPITAL focal point of the hospital complex, the modular building exterior included a 4” brick facade and a 4’ high mansard roof. The mansard roof acted both as an equipment screen and cover for the walkway that went from the employee entrance to the main entrance of the building. In addition, an exterior glass vestibule was utilized and served as a windbreak....

 Open the catalog to page 2

All Williams Scotsman catalogs and technical brochures

Archived catalogs

  1. FBI Academy

    2  Pages

*Prices are pre-tax. They exclude delivery charges and customs duties and do not include additional charges for installation or activation options. Prices are indicative only and may vary by country, with changes to the cost of raw materials and exchange rates.