1. Catalogs
  2. Tilon CG Ltd
  3. RESTORATION OF THE FORTH BRIDGE

RESTORATION OF THE FORTH BRIDGE

RESTORATION OF THE FORTH BRIDGE

RESTORATION OF THE FORTH BRIDGE

Product catalog summary
Restoration Overview
The restoration of the Forth Bridge, completed in December 2011, was a decade-long project costing £130 million. It involved repairing and repainting the bridge for the first time in its 121-year history, using innovative scaffolding and encapsulation techniques to protect this Grade A listed Victorian engineering icon.

Project Planning and Execution
The project was divided into three main components: ensuring safe access, replacing corroded steel, and applying a high-tech three-coat paint system. Balfour Beatty, the principal contractor, implemented procedures to ensure safety and prevent environmental contamination.

Logistics and Challenges
Complex logistics were required to minimize disruption to rail services, with up to 200 train movements daily. Innovative scaffolding systems provided access to all bridge areas, with materials often moved by barge or along the railway line during specific time windows.

Specialist Skills and Workforce
At its peak, the project employed up to 400 tradesmen, including scaffolders, blasters, and coaters. Specialist abseilers were used for inaccessible tasks, and the workforce had to constantly adjust to weather challenges to ensure safety.

Scaffolding and Encapsulation
Scaffolding systems were customized to the bridge's structure, supported from welded pads and support points. The encapsulation system created controlled environments for safe working conditions and prevented contamination.

Blasting and Painting
Blasters used recycled grit to remove old paint and rust, and the bridge was recoated with a specially developed paint for long-term protection.

Conclusion
The restoration of the Forth Bridge was a significant engineering achievement, ensuring the bridge remains a symbol of engineering excellence and a fully functioning railway crossing.
Introduction
The document discusses the restoration of the Forth Bridge using a specialized three-part coating system developed by Sherwin Williams, designed for severe marine environments and verified to last at least 20 years.

Coating System Specifications
The coating process starts with a zinc phosphate holding primer, followed by a 'stripe coat' of high-build epoxy glass flake paint for barrier protection. The entire surface is sprayed with the coating to a minimum thickness of 400 microns, and a topcoat of 'Forth Bridge Red' acrylic urethane is applied for color stability.

Application Process
Each bridge section undergoes inspection before dismantling scaffolding and moving to the next area. The project used 240,000 liters of paint to recoat the bridge, enhancing its appearance for potential UNESCO World Heritage status.

Technological Advancements
Developed by Leighs Paints, the system binds with metal to prevent moisture penetration, with a finish coat offering good color and gloss retention.

Apprenticeship Program
The document highlights an engineering apprenticeship scheme in the UK, training over 1,000 apprentices in various skills, contributing to significant engineering projects. The program has received a Grade 1 from OFSTED for its quality.

Conclusion
This restoration project not only preserves the Forth Bridge but also showcases modern engineering techniques and training programs that support the UK's engineering sector.
See more

Catalog excerpts

RESTORATION OF THE FORTH BRIDGE-1

RESTORATION OF THE FORTH BRIDGE The seemingly never-ending job of painting the Forth Bridge is coming to an end. The logistics and challenges behind the successful conclusion of the 10-year project to restore the bridge are outlined by John Andrew, the Business Development Director for Balfour Beatty Regional Civil Engineering, the principal contractor for the Forth Bridge Restoration Contract. RESTORATION OF THE FORTH BRIDGE 14 The Forth Bridge viewed from North Queensferry following the completion of the restoration works, November 2011 © John Andrew INGENIA ISSUE 49 DECEMBER 2011

 Open the catalog to page 1
RESTORATION OF THE FORTH BRIDGE-2

RESTORATION OF THE FORTH BRIDGE December 2011 saw the completion of a decade-long project to repair and completely repaint the Forth Bridge for the first time in its 121 years of operation. The restoration works involved one of the largest-scale tasks of its kind, featuring innovative scaffolding techniques and encapsulation methods that have since been replicated on other large civil engineering and building projects. The Forth Bridge, which opened in 1890, had never before been subjected to this level of treatment. The logistics for this £130 million project, on the world’s first cantilever...

 Open the catalog to page 2
RESTORATION OF THE FORTH BRIDGE-3

RESTORATION OF THE FORTH BRIDGE At all times during the restoration process, the structural integrity of the bridge was the primary consideration as the weather-resistant plastic membrane could have acted as a 'sail7and created additional wind loads to the structure. WEATHER The elements posed a constant challenge as the Forth Bridge can experience the weather of all four seasons in one day with conditions changing in a matter of minutes. Supervisors regularly checked that wind speeds were within agreed limits to ensure safe working conditions. When necessary, the scale of the bridge allowed...

 Open the catalog to page 3
RESTORATION OF THE FORTH BRIDGE-4

We run one of the largest engineering apprenticeship schemes in the UK helping people develop a range of skills from sheet metalworking to design engineering. As part of their three-year course, our apprentices also get to work on some of the country’s most exciting engineering projects like the Astute submarine programme and the Typhoon combat aircraft. It’s this dedication that led OFSTED to award us a Grade 1 for our apprentice training programme. RESTORATION OF THE FORTH BRIDGE of global US coatings specialist Sherwin Williams. The three-part coating system originated from the North Sea oil...

 Open the catalog to page 4

All Tilon CG Ltd catalogs and technical brochures

  1. SUPADEK

    1  Page

*Prices are pre-tax. They exclude delivery charges and customs duties and do not include additional charges for installation or activation options. Prices are indicative only and may vary by country, with changes to the cost of raw materials and exchange rates.