General Contractor?s Guide for Constructing & Sealing Access Floor Air Plenums
6Pages

{{requestButtons}}

Catalog excerpts

General Contractor?s Guide for Constructing & Sealing Access Floor Air Plenums - 1

Access Floors General Contractor’s Guide for Constructing & Sealing Access Floor Air Plenums Access Floors to the Power of

Open the catalog to page 1
General Contractor?s Guide for Constructing & Sealing Access Floor Air Plenums - 2

Education and accountability are key to constructing an access floor air plenum.

Open the catalog to page 2
General Contractor?s Guide for Constructing & Sealing Access Floor Air Plenums - 3

GC’s Guide for Constructing & Sealing Access Floor Air Plenums Plenum Integrity is one of the most important aspects of designing, constructing and maintaining an underfloor air delivery (UFAD) system. It is vital that the entire design and construction team does their part to ensure the underfloor plenum is sealed properly. As the general contractor you have the responsibility of ensuring all the subcontractors are informed of, and perform to the sealing requirements as described in the specifications and details provided by the architect. To ensure the UFAD system operates as intended...

Open the catalog to page 3
General Contractor?s Guide for Constructing & Sealing Access Floor Air Plenums - 4

3. Plenum Mockup and Testing: You will need to coordinate and schedule all successful bidders to take part in building an on-site access floor plenum mockup in accordance with the design specifications and construction details for inspection and air leakage testing. The mockup should be representative of all scenarios present in the final structure including, but not limited to: at least one sheetrock wall with sealed joints below the access floor, sealed access floor perimeters, a sealed plenum divider, floor covering (and cove base if required), air diffusers, power/voice distribution...

Open the catalog to page 4
General Contractor?s Guide for Constructing & Sealing Access Floor Air Plenums - 5

Electrical System Location of Seal Conduit through plenum walls. Open ends of conduits in the plenum space. Remediation Required Voice/Data System (Communications) Location of Seal Cable penetrations through the plenum walls with cable sleeves. Caps on empty conduits or cable sleeves. Remediation Required Access Floor Location of Seal Remediation Required ZONE PARTITIONING Plenum dividers. Penetrations through plenum dividers. ABUTMENTS Perimeter seam without wall base. Through wall without wall base. Perimeter seam with wall base. Through wall with wall base. Perimeter seam at non-smooth...

Open the catalog to page 5
General Contractor?s Guide for Constructing & Sealing Access Floor Air Plenums - 6

Tate Access Floors, Inc. Corporate Headquarters: 7510 Montevideo Road, Jessup, MD 20794 Tate Hotline: 1-800-231-7788 Tel: 410-799-4200 Fax: 410-799-4207 Production Facilities: 7510 Montevideo Road, Jessup, MD 20794 52 Springvale Road, Red Lion, PA 17356 International Sales & Support Office: 169 Jalan Jurong Kechil #7-011, Sherwood Singapore 598669 Tel: 65-6468-1332 Fax: 65-6468-6681 tateglobal.com kingspan.com tateaccessfloors.com kingspan.com Tate Access Floors, Inc. components are proudly made in the U.S.A. Tate ASP Access Floors, Inc. Canadian Office & Production Facilities: 880...