Introduction
Plenum integrity is crucial for the effective operation of an underfloor air delivery (UFAD) system. The general contractor (GC) is responsible for ensuring that all subcontractors adhere to the sealing requirements specified by the architect to maintain plenum integrity.

Key Recommendations
  • Design: Review project specifications and construction details with the architect before issuing construction documents.
  • Pre-Bid Meeting: Inform all subcontractors of the plenum sealing requirements and mock-up needs.
  • Pre-Construction: Reaffirm plenum sealing requirements for each division in a pre-construction meeting.
  • Mock-up: Construct and test a mock-up that reflects actual building conditions related to the UFAD system.
  • Quality Inspections: Ensure subcontractors address any issues identified during inspections before access floor installation.

General Contractor Guidelines
The GC should ensure the following actions are completed:
  • Pre-Bid Meetings: Use CSI specifications and plenum details to solicit bids and inform divisions about mock-up requirements.
  • Pre-Construction Meetings: Reaffirm the importance of plenum sealing integrity and ensure contractors have the necessary drawings and specifications.
  • Plenum Mockup and Testing: Coordinate the construction of an on-site access floor plenum mockup for inspection and air leakage testing.
  • Auditor Coordination: Work with an independent quality auditor to verify compliance with specifications and drawing details.
  • Testing: Conduct air leakage tests on the mock-up and finished plenum to meet project requirements.
  • Remediation: Ensure subcontractors address any issues identified during inspections and testing.

Plenum Inspections & Reporting
A checklist for inspections includes verifying the sealing of various structures, seams, penetrations, and openings. Inspections should be coordinated with the GC and conducted throughout the construction process.

Contact Information
Tate Access Floors, Inc. provides contact details for their corporate headquarters, production facilities, and international sales offices.
See more

Catalog excerpts

General Contractor?s Guide for Constructing & Sealing Access Floor Air Plenums-1

Access Floors General Contractor’s Guide for Constructing & Sealing Access Floor Air Plenums Access Floors to the Power of

 Open the catalog to page 1
General Contractor?s Guide for Constructing & Sealing Access Floor Air Plenums-2

Education and accountability are key to constructing an access floor air plenum.

 Open the catalog to page 2
General Contractor?s Guide for Constructing & Sealing Access Floor Air Plenums-3

GC’s Guide for Constructing & Sealing Access Floor Air Plenums Plenum Integrity is one of the most important aspects of designing, constructing and maintaining an underfloor air delivery (UFAD) system. It is vital that the entire design and construction team does their part to ensure the underfloor plenum is sealed properly. As the general contractor you have the responsibility of ensuring all the subcontractors are informed of, and perform to the sealing requirements as described in the specifications and details provided by the architect. To ensure the UFAD system operates as intended after...

 Open the catalog to page 3
General Contractor?s Guide for Constructing & Sealing Access Floor Air Plenums-4

3. Plenum Mockup and Testing: You will need to coordinate and schedule all successful bidders to take part in building an on-site access floor plenum mockup in accordance with the design specifications and construction details for inspection and air leakage testing. The mockup should be representative of all scenarios present in the final structure including, but not limited to: at least one sheetrock wall with sealed joints below the access floor, sealed access floor perimeters, a sealed plenum divider, floor covering (and cove base if required), air diffusers, power/voice distribution boxes,...

 Open the catalog to page 4
General Contractor?s Guide for Constructing & Sealing Access Floor Air Plenums-5

Electrical System Location of Seal Conduit through plenum walls. Open ends of conduits in the plenum space. Remediation Required Voice/Data System (Communications) Location of Seal Cable penetrations through the plenum walls with cable sleeves. Caps on empty conduits or cable sleeves. Remediation Required Access Floor Location of Seal Remediation Required ZONE PARTITIONING Plenum dividers. Penetrations through plenum dividers. ABUTMENTS Perimeter seam without wall base. Through wall without wall base. Perimeter seam with wall base. Through wall with wall base. Perimeter seam at non-smooth walls...

 Open the catalog to page 5
General Contractor?s Guide for Constructing & Sealing Access Floor Air Plenums-6

Tate Access Floors, Inc. Corporate Headquarters: 7510 Montevideo Road, Jessup, MD 20794 Tate Hotline: 1-800-231-7788 Tel: 410-799-4200 Fax: 410-799-4207 Production Facilities: 7510 Montevideo Road, Jessup, MD 20794 52 Springvale Road, Red Lion, PA 17356 International Sales & Support Office: 169 Jalan Jurong Kechil #7-011, Sherwood Singapore 598669 Tel: 65-6468-1332 Fax: 65-6468-6681 tateglobal.com kingspan.com tateaccessfloors.com kingspan.com Tate Access Floors, Inc. components are proudly made in the U.S.A. Tate ASP Access Floors, Inc. Canadian Office & Production Facilities: 880 Equestrian...

 Open the catalog to page 6
*Prices are pre-tax. They exclude delivery charges and customs duties and do not include additional charges for installation or activation options. Prices are indicative only and may vary by country, with changes to the cost of raw materials and exchange rates.