Commissioning Agent?s Guide for Inspecting & Testing Access Floor Air Plenums

Product catalog summary
Overview: This document serves as a guide for commissioning agents tasked with inspecting and testing access floor air plenums, specifically focusing on maintaining plenum integrity in underfloor air delivery (UFAD) systems. It highlights the critical role of proper sealing and provides comprehensive recommendations and procedures for effective inspection and testing.
Key Recommendations:
  • Design: Collaborate with architects to review project specifications before finalizing construction documents.
  • Pre-Bid: Engage in meetings to educate subcontractors about sealing requirements.
  • Pre-Construction: Reiterate sealing requirements during pre-construction meetings.
  • Mock-up: Perform inspections and air leakage testing on a mock-up that simulates typical building conditions.
  • Quality Inspections: Conduct frequent inspections throughout construction to ensure adherence to construction documents.
  • Testing: Execute air leakage tests to verify compliance with performance standards.
  • Reporting: Deliver prompt reports on any sealing deficiencies identified.
Inspection and Reporting Procedures: The guide provides a checklist for inspecting structures, seams, penetrations, and openings to ensure plenum integrity. It advises coordinating inspections with the general contractor and conducting them early to prevent delays.
Systems Inspections:
  • Base Building Core and Shell: Inspect construction, seams, and penetrations prior to access floor installation.
  • HVAC System: Early inspection of sealed spaces around ducts and penetrations is recommended.
  • Plumbing and Electrical Systems: Inspect sealed spaces around pipes and conduits early to avoid interference with floor installation.
  • Voice/Data System: Inspect sealed spaces around cables before floor installation.
Air Leakage Test Procedures: The guide details procedures for testing two categories of air leakage:
  • Category 1 Leakage: Occurs outside the intended occupied zone. The test involves pressurizing the plenum and measuring the CFM needed to maintain pressure, subtracting panel seam leakage to assess compliance.
  • Category 2 Leakage: Occurs within the occupied zone through unintended spaces. The test involves sealing air delivery devices and measuring total leakage, subtracting Category 1 leakage to assess compliance.
Remediation Techniques: In cases of excessive leakage, techniques such as smoke tests and thermal imaging can be employed to identify leak locations.
See more

Catalog excerpts

Commissioning Agent?s Guide for Inspecting & Testing Access Floor Air Plenums-1

Access Floors Commissioning Agent’s Guide for Inspecting & Testing Access Floor Air Plenums Access Floors to the Power of 1

 Open the catalog to page 1
Commissioning Agent?s Guide for Inspecting & Testing Access Floor Air Plenums-2

Proper inspection and testing of the underfloor air plenum is the best way to ensure plenum integrity.

 Open the catalog to page 2
Commissioning Agent?s Guide for Inspecting & Testing Access Floor Air Plenums-3

Commissioning Agent’s Guide for Inspecting & Testing Access Floor Air Plenums Plenum Integrity is one of the most important aspects of designing, constructing and maintaining an underfloor air delivery (UFAD) system. It is vital that the entire design and construction team does their part to ensure the underfloor plenum is sealed properly. As the commissioning agent, you have the responsibility to review, inspect, test, and report as outlined in the projects specifications any plenum integrity sealing deficiencies To this end, Tate Access Floors is providing the following Commissioning Agent’s...

 Open the catalog to page 3
Commissioning Agent?s Guide for Inspecting & Testing Access Floor Air Plenums-4

Base Building Core and Shell Inspect the construction, seams and penetrations of these building core and shell elements before any access floor components are installed. Conduct inspections as early as possible before the scheduled start of access floor installation so that corrective measures, if necessary, will not delay schedules. Location of Seal Perimeter seam along slab and exterior wall. Enclosed column seam at slab line. Drywall partition condition at slab line. Base of stair landing. Elevator shaft below access floor line. Expansion joint in concrete deck. Remediation Required HVAC System...

 Open the catalog to page 4
Commissioning Agent?s Guide for Inspecting & Testing Access Floor Air Plenums-5

Voice/Data System (Communications) Inspect the sealed annular space around cables in plenum walls before any access floor components are installed. Conduct inspections of plenum wall penetrations as early as possible before the scheduled start of access floor installation so that corrective measures, if necessary, will not interfere with floor installation. Location of Seal Cable penetrations through the plenum walls with cable sleeves. Caps on empty conduits or cable sleeves. Remediation Required Access Floor The zone partitioning inspections should be held prior to completion of the floor panel...

 Open the catalog to page 5
Commissioning Agent?s Guide for Inspecting & Testing Access Floor Air Plenums-6

Air Leakage Test Procedures Access Floor Air Plenum Leakage Categories There are two basic categories of UFAD air leakage, Category 1 leakage occurs outside of the intended occupied zone, Category 2 leakage is plenum air that leaks into the occupied zone through spaces other than the designed air distribution devices such as diffusers. Category 2 leakage is unique to UFAD systems because all of this leakage goes into the occupied space whereas in a traditional ducted overhead system, all leakage and short-circuited air enters the return plenum and will not reached the intended zone. Category...

 Open the catalog to page 6
Commissioning Agent?s Guide for Inspecting & Testing Access Floor Air Plenums-7

Category 2 Leakage: Category 2 air leakage allowable limit will be based on the project specifications. If category 2 leakage is beyond the specified limit, the plenum should be repaired to yield leakage of no more than the specified limit. Category 2 Air Leakage Test Procedures: Tate recommends the following procedure for testing category 2 air leakage during the mock-up and final plenum commissioning stages: Category 2 testing shall use the access floor air plenum assembled as described in category 1 testing however all cutouts, accessories, and carpeting shall be installed as per the project...

 Open the catalog to page 7
Commissioning Agent?s Guide for Inspecting & Testing Access Floor Air Plenums-8

UFAD Air Leakage Testing Report General Testing Information Date of air leakage testing: Project Name: South Development Building 1 Project Number: Location of test area: 3rd Floor Southeast Wing Determine Maximum Allowable Category 1 Air Leakage (CFM) 1. Total square foot of test area………… . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .………… 5,000 ft2 2. Total number of diffusers designed for test area . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .40 3. Design static pressure per project specifications . . . . . . . . . . . . . . . ....

 Open the catalog to page 8
Commissioning Agent?s Guide for Inspecting & Testing Access Floor Air Plenums-9

Tate’s Panel Seam Leakage Chart Average Panel Gap (inches) UFAD Air Leakage Remediation In the event that excessive category 1 leakage is discovered during plenum testing there are several techniques that have been used to help identify the location of a leak. One common method is to conduct a smoke test. A smoke test is performed by blowing smoke into the floor plenum and then looking for places where the smoke is escaping. By removing panels in this location the point of leakage is easier to find. Thermal Imaging Another option is to conduct a thermal scan of the interior spaces. Thermal imaging...

 Open the catalog to page 9
Commissioning Agent?s Guide for Inspecting & Testing Access Floor Air Plenums-10

Tate Access Floors, Inc. Corporate Headquarters: 7510 Montevideo Road, Jessup, MD 20794 Tate Hotline: 1-800-231-7788 Tel: 410-799-4200 Fax: 410-799-4207 Production Facilities: 7510 Montevideo Road, Jessup, MD 20794 52 Springvale Road, Red Lion, PA 17356 International Sales & Support Office: 169 Jalan Jurong Kechil #7-011, Sherwood Singapore 598669 Tel: 65-6468-1332 Fax: 65-6468-6681 tateglobal.com kingspan.com tateaccessfloors.com kingspan.com Tate Access Floors, Inc. components are proudly made in the U.S.A. Tate ASP Access Floors, Inc. Canadian Office & Production Facilities: 880 Equestrian...

 Open the catalog to page 10
*Prices are pre-tax. They exclude delivery charges and customs duties and do not include additional charges for installation or activation options. Prices are indicative only and may vary by country, with changes to the cost of raw materials and exchange rates.