Mushrif Water Reservoir Phases 4, 5
8Pages

{{requestButtons}}

Catalog excerpts

Mushrif Water Reservoir Phases 4, 5 - 1

Mushrif Water Reservoir Phases 4, 5 and 6 Progress is built on ideas.

Open the catalog to page 1
Mushrif Water Reservoir Phases 4, 5 - 3

Mushrif Water Reservoir Phases 4, 5 and 6 (180 Million Gallon) On the outskirts of Dubai the world’s largest drinking water reservoir has been built by Max Bogl. Dubai Electricity and Water Authority (DEWA) have invested approx­mately 600 mili lion AED in the construction of three new tanks with a capacity of 820 million litres of drinking water. The Reservoir is supplied with water from the desalination plant located in the Jebel Ali district 35 km away. The new Reservoir is crucial for the water supply to the close-by districts of Dubai. During a construction period of approximately...

Open the catalog to page 3
Mushrif Water Reservoir Phases 4, 5 - 4

30,000 to of reinforced steel was installed. Construction Concept The reinforced concrete Reservoir is built on a 33 km drainage system. The purpose of it is to observe leak tightness and to drain potentially accumulated water in order to prevent structural damages. Each of the three storage tanks measures 375 m x 175 m with a depth of 5,5 m. The Tanks are partitioned into 4 compart­ ments, which are further divided into 8 smaller sections by 9,500 running metres of running walls.

Open the catalog to page 4
Mushrif Water Reservoir Phases 4, 5 - 5

One million cubic metres of desert sand was excavated. 4,500 pieces of precast beams and 6,000 columns were erected. New pipes and chambers were connected with the existing network. 20,000 pieces filigran elements

Open the catalog to page 5
Mushrif Water Reservoir Phases 4, 5 - 6

In order to ensure leak tightness 40 km of waterstop and 300,000 m² PVC membranes were installed. After completion of the shell and core works all tanks underwent a series of leak tightness tests, with 65 million litres of water. A network of approximately 100 fully automated valves enabled the supervision of the supply and drain of drinking water from a centralised control centre. Up-to-date measuring instruments allow a fully automated control of water quality, water pressure and water levels in the tanks as well as a CCTV system covering the entire site.

Open the catalog to page 6
Mushrif Water Reservoir Phases 4, 5 - 7

Tight Program To achieve the Program 2,000 labourers were working 24 hours per day, 7 days a week. At the peak of the construction 13 Tower cranes were operating with outside temperatures of up to 50°C. In order to provide the construction site with the necessary daily quantity of 1,000 m³ concrete, a batching plant was erected directly on site. To assure safety for the entire work force throughout all construction phases was indeed a highly challenging task. Due to regular site inspections carried out by safety and health protection experts and safety training provided for all labourers...

Open the catalog to page 7
Mushrif Water Reservoir Phases 4, 5 - 8

Technical Data Plant gross area: Number of Storage Tanks: Measure of each tank: Capacity of Storage water: Construction period: Client: Dubai Electricity & Water Authority Client Consultant Manager PCM: Nippon Jogesuido Sekkai Consultants NJS Max Bogl Emirates Building Contracting LLC Iridium Building 1st Floor, Office – 127 Max Bogl Emirates Building Contracting LLC Al Ghaith Holding Tower 11th Floor, Office – 1114 info@max-boegl.com www.max-boegl.com info@max-boegl.com www.max-boegl.com General Contractor: Max Bogl Emirates Building Contracting LLC