CETRIS® PDI is a two-ply panel used in dry floor technology, consisting of a 22 mm thick cement bonded particleboard glued to a 12 mm insulating fibreboard. The panels measure 1,220 × 610 mm with a thickness of 34 mm, featuring tongue and groove edges for easy installation. They are designed to spread spot-load stress over a larger area.

Packing and Storage
The panels are packed on wooden pallets for forklift handling and secured with straps. They are protected by PE foil but should be stored in a sheltered, dry area to prevent moisture damage, especially to the fibreboard. Panels can be stacked two layers high on pallets.

Floor Structures and Installation
CETRIS® PDI panels can be laid directly on a level, dry base such as a ceiling structure or cladding. For increased structural height or thermal resistance, insulation boards can be placed under the panels. The maximum recommended thickness for insulation boards is 50 mm.

Floor Loading Capacity
The panels have been tested for concentrated and impact loads as per EN 13 810-1, showing high load capacity and resistance to spot stress. They are suitable for various load categories, including areas with tables, fixed seats, and public gathering spaces.

Sound and Thermal Insulating Properties
The acoustic and thermal properties of floors made with CETRIS® PDI panels are determined by the insulation board properties. The panels provide sound insulation and improved thermal resistance.

Preparation and Laying Procedure
The base must be dry and level, with a maximum surface unevenness of 4 mm per 2 metres. Levelling can be done using wet or dry methods. Before laying, panels should acclimatize for 48 hours at a minimum temperature of 18°C. Moisture insulation is necessary to prevent moisture transport into the insulation layer.

Installation Steps
1. Lay panels after finishing wet building works.
2. Ensure the base is dry and clean.
3. Acclimatize panels before installation.
4. Use PE foil for moisture insulation if necessary.
5. Level the base if required.
6. Determine the laying direction of insulation boards.
7. Maintain a 15 mm dilatation gap along vertical structures.
8. Lay panels from right to left, ensuring no cross-joints.
9. Glue panels using polyurethane glue.
10. Allow glue to set for 24 hours before loading the floor.

Additional Considerations
For large areas, sequential installation is recommended to prevent damage. The floor can be fully loaded after the glue sets. Local fastening may be needed to prevent edge lifting during drying.
See more

Catalog excerpts

Floor panel CETRIS® PDI-1

Floor panel CETRIS® PDI is a two-ply panel used in dry floor technology. It consists of a 22 mm thick cement bonded CETRIS® particleboard glued to 12 mm insulating fibreboard (hardboard). The size is 1,220 x 610 mm (including the tongue) and it is 34 mm thick; it has a tongue and groove along the perimeter, the surface is smooth. The panels should be laid on a level surface area (ceiling structures, cladding). They are great for a quick and exact installation. They also spread spot-load stress over a larger area. Technical specification CETRIS® PDI floor panels are laid on wooden transport pallets, which enable forklift manipulation. The boards are secured with straps. CETRIS® PDI panels are protected against atmospheric influences by PE foil. Wrapping in PE foil, however, does not satisfy conditions for long-lasting exposure to atmospheric influences when stored in an open area. CETRIS® PDI panels must be stored in a sheltered dry area so that they do not get wet before laying (especially the fibreboard). When storing, CETRIS® PDI panels on the pallets can be stacked two layers high. The boards should be placed on the pallets when handled. They should be hand-carried in a vertical position. Floor structures with CETRIS® PDI panels CETRIS® PDI panels can be laid directly on the base - a ceiling structure or cladding. The base must be level, supporting and dry. In this way, a new load spreading and insulating layer only 34 mm thick can be made with a high load capacity and resistance against spot stress. If a higher structural height has to be achieved, or if the floor structure must reach a higher thermal resistance value, we recommend laying insulation boards under the CETRIS® PDI panels. Polystyrene based insulation boards (min. class EPS S 70), or boards with stone or mineral wool or fibreboards are suitable. However, they must always be designed for light floating floors. The maximum recommended thickness of the insulation board is 50 mm. The biggest cement bonded particleboard producer in Europe.

 Open the catalog to page 1
Floor panel CETRIS® PDI-2

Floor loading capacity The loading capacity of CETRIS® PDI panels was determined by tests specified for light floor structures as per EN 13 810-1. The testing was performed in an acoustic chamber of the SCI (Zlfn branch) on 3.6 x 3.0 m samples. The floor was always laid on a 140 mm thick reinforced concrete ceiling structure. The test loading methods were as follows: • Concentrated load - action of a spot load 130 kg (260 kg) in a circular area 25 mm in diameter. The critical sag value under the loading arm is 3 mm. • Impact load - a 40 kg load was dropped from the height of 350 mm; the critical...

 Open the catalog to page 2
Floor panel CETRIS® PDI-3

Without a feather on the longitudinal side Moisture of the base The maximum allowable specific moisture of the base: Insulation against moisture To eliminate transport of moisture into the thermal and sound insulation layer, this layer must be separated from the floor structure by a protective foil. This protection concerns mainly a support ceiling structure, which contains residual moisture or areas where increased penetration Laying CETRIS® PDI floor panels 1 Floating floors made with CETRIS® PDI are laid as a final layer after finishing «wet» building works (after finishing walls, plastering,...

 Open the catalog to page 3
Floor panel CETRIS® PDI-4

Floor systems CETRIS® Cement-bonded particleboard The floor panels must be glued at a maximum relative air humidity of 80 % and a minimum room temperature of 5° C. The CETRIS® PDI panels must be in full contact with each other. Doorsillless floor transition 01 Dilatation section Schlüter DILEX 02 Doorsill link of the doorframe 03 Wooden base section under the doorframe 04 Wear layer 05 Floor panel CETRIS® PDI 06 Vapor barrier 07 Dilatation gap 15 mm 08 Ceiling structure Vertical cross-section When laying down the final panel, first cut it to the required length, then cut the tongue on the longitudinal...

 Open the catalog to page 4
*Prices are pre-tax. They exclude delivery charges and customs duties and do not include additional charges for installation or activation options. Prices are indicative only and may vary by country, with changes to the cost of raw materials and exchange rates.