| Clearances The position of the boiler must be such that there is adequate space for servicing. The recommended clearances are: 50 mm either side of the boiler. 600 mm at the front of the boiler. 300 mm below the boiler. • Place template on wall in required position, noting that hanging bracket must be 780 mm above centre line of pipework, making allowances for the necessary clearances etc. Note: It is permissible to install the boiler with reduced clearances at the bottom and sides of the boiler PROVIDING adequate consideration is given for Servicing/Repairs at a later date. If any doubt exists, contact Saunier Duval Technical Helpline 01773 828400. • Mark position of the holes for the hanging bracket. • Drill, plug and fix the hanging bracket to the wall using suitable screws. • Check that the hanging bracket is level. • For horizontal flue system, mark the position for the flue hole as follows: Flue to rear of boiler • Mark correct position of hole from template. |