56 cm61 cm 15.2 cm >
THE ONLY PATENTED PREFABRICATEDNATURAL STONE PANEL
Cement baseNaturalStoneMetal grill >
1
Cover the fixing areas with adhesive* using a toothed trowel (6-7 mm). Once theadhesive has been applied it maximum life expectancy is 40 minutes.
FIXING GUIDETraditional installation
* Fixing recommendations:Adhesive made from a cement base that isapproved for thicknesses of 3mm to 15mm
Non-sliding and heat resistant
Adhesion according to EN1348 (N/mm 2 )After 28 days2.6 N/mm 2 After being heated2.5 N/mm 2 2
Fix in place using a rubber mallet.At the end of each row, adjust the
panel length by using a radial saw.
3
Finish of the corners in accordance with the diagram.
Corner pieces: Two sizes are availablein order to be able to vary the joints. 61 cm 30.5 cm For heights above 2 m a mechanicalfixing system is recommended.
FIXING GUIDEInstallation with hooks
1
Drill four holes on each Stonepanel as indicated.
Drill or cut a spaceto fix a hook. 10 cm Two holes on topTwo holes on the bottom 41 cm Drill 0<4 mm 2.5 cm1 cm >
2
Drill holes on the top edge of each panel for the hooks. The holes need to be free of dust.Proceed as in step 1 of the traditional fixing method and fix the hooks to the wall and the Stonepanel.
Hook (Stainless steel 304) Drill hole • The hooks should bemade from stainlesssteel 304. They can alsobe made from steelwire or from hooks thatare traditionally used in
slate roof construction.The sizes of the hooksare: mín.1.5 cm Adhesive cap 2 cm Support wall mín. 8 cm CUPAMAT, S.A. •